Anyone know the latest on the new Edge?
Do you know who the A/E is? The first renderings were pretty cool lookingStill in design phase. Money has been raised and construction will begin when design is finalized. 12-18 months construction time frame once it begins.
Do you know who the A/E is? The first renderings were pretty cool looking
So the 176 mil was just a promise not actual gifts?All the money is not in the bank.
We'll see. Our projects right now are approximately 150% higher construction cost than pre-pandemic. That's 2.5 times the cost of 2019 prices. I'm so tired of being the "low bidder" (as the designer providing estimates). And to make matters worse, they are taking 50% longer to complete because the materials are not available - everything from PVC pipe to pumps to electrical parts/controls - you name it, which tends to create additional costs from extra time for construction observation, etc. It used to be a delay in materials was "you'll get it in 14-16 weeks". Now that's the starting point with some items taking 8 months to be delivered. While an annoyance for me, I'd hate to be a contractor right now trying to schedule out work.The money is there. As always in large fundraising drives, there is some money that is promised, but I wouldn't worry about it. ALL the necessary money is pretty much available now. We had a goal of 125 million. We raised just over 175 million. With over 50 million extra raised, we don't need to worry about whether all promised funds are actualized before beginning. The EDGE center was projected at 70 million and 85 million was donated for it. For once, money is not the issue.
Ug. Tell me about it. Steel prices went up 2.5% per month last year. A project we are working on is up well over 50% of the initial estimate from last spring. This is what's going to burst the bubble...inflation will put a stop to new construction projects, which will see a huge drop in jobs that just cascades.We'll see. Our projects right now are approximately 150% higher construction cost than pre-pandemic. That's 2.5 times the cost of 2019 prices. I'm so tired of being the "low bidder" (as the designer providing estimates). And to make matters worse, they are taking 50% longer to complete because the materials are not available - everything from PVC pipe to pumps to electrical parts/controls - you name it, which tends to create additional costs from extra time for construction observation, etc. It used to be a delay in materials was "you'll get it in 14-16 weeks". Now that's the starting point with some items taking 8 months to be delivered. While an annoyance for me, I'd hate to be a contractor right now trying to schedule out work.
The money is there. As always in large fundraising drives, there is some money that is promised, but I wouldn't worry about it. ALL the necessary money is pretty much available now. We had a goal of 125 million. We raised just over 175 million. With over 50 million extra raised, we don't need to worry about whether all promised funds are actualized before beginning. The EDGE center was projected at 70 million and 85 million was donated for it. For once, money is not the issue.
So the 175 million dollars is in a bank earning interest, not a great amount but it will mean more money when we do start vs if we just kept the 175 mil in the checking account.We'll see. Our projects right now are approximately 150% higher construction cost than pre-pandemic. That's 2.5 times the cost of 2019 prices. I'm so tired of being the "low bidder" (as the designer providing estimates). And to make matters worse, they are taking 50% longer to complete because the materials are not available - everything from PVC pipe to pumps to electrical parts/controls - you name it, which tends to create additional costs from extra time for construction observation, etc. It used to be a delay in materials was "you'll get it in 14-16 weeks". Now that's the starting point with some items taking 8 months to be delivered. While an annoyance for me, I'd hate to be a contractor right now trying to schedule out work.
So the 175 million dollars is in a bank earning interest, not a great amount but it will mean more money when we do start vs if we just kept the 175 mil in the checking account.
Better to use that money to buy players and coaches.
Go Jackets!
Anyone have up to date artist renderings ?
Just noticed this in an email they sent me. I don't know which Design I prefer but they both look sharp.moving along....slowly.....
Board of Regents Approves Student-Athlete Performance Center
Tech athletics receives go-ahead to proceed with transformative new facility for student-athletesramblinwreck.com